Expansion of the Hydropower Plant in Utoqqarmiut Kangerluarsunnguat
Expansion of the Utoqqarmiut Kangerluarsunnguat (Buksefjord) Hydropower Plant by 76.9 MW
Expansion of the Hydropower Plant in Utoqqarmiut Kangerluarsunnguat
Expansion of the Utoqqarmiut Kangerluarsunnguat (Buksefjord) Hydropower Plant by 76.9 MW
Expansion of the Hydropower Plant in Utoqqarmiut Kangerluarsunnguat
Expansion of the Utoqqarmiut Kangerluarsunnguat (Buksefjord) Hydropower Plant by 76.9 MW
Expansion of the Hydropower Plant in Utoqqarmiut Kangerluarsunnguat
Expansion of the Utoqqarmiut Kangerluarsunnguat (Buksefjord) Hydropower Plant by 76.9 MW
Expansion of the Hydropower Plant in Utoqqarmiut Kangerluarsunnguat
Expansion of the Utoqqarmiut Kangerluarsunnguat (Buksefjord) Hydropower Plant by 76.9 MW

NunaGreen is expanding the existing hydropower plant at Utoqqarmiut Kangerluarsunnguat (Buksefjord) near Nuuk

The project includes the construction of a new power station at the lake Kangerluarsunnguup Tasersua, which will be equipped with new turbines with a total capacity of 76.9 MW, as well as a 16 km transfer tunnel connecting the two lakes, Kangerluarsunnguup Tasersua and Isortuarsuup Tasia, to ensure water supply for the new power station.

The new power station will be connected to the existing plant via a 37 km transmission line. With the expansion, the total capacity will nearly triple from 45 Megawatts to 121 Megawatts, thereby securing Nuuk’s supply of renewable energy for many decades to come.

The project is tendered as a turnkey contract, with construction expected to begin in 2026, and the new hydropower plant anticipated to be commissioned in 2032.

Construction Road

The upgrade of the existing road at the Buksefjord Plant, as well as the establishment of a new construction road providing access to the future project area, was tendered as a main contract in 2025. The contract was won by the local contractor GNC, which made full use of the 2025 construction season. In total, 14 km of existing road were rehabilitated, and nearly 5 km of new construction road were built. This provides the turnkey contractor with a solid foundation when the construction season begins in 2026.

VVM-redegørelse

Se VVM redegørelse og VVM-godkendelse for projektet her.